Update on first LONDINIUM R build

by Reiss Gunson on Tuesday, 17 January 2017 13:58

i have received a few emails this morning from customers enquiring of how the LONDINIUM R build is progressing

we have lost a week as a result of discovering that we did not have the correct pump mounts in stock

however i was pleased to awake to the following update this morning;

Hi Reiss,
I have sourced some anti vibration mountings from elsewhere and these will arrive today. Production starts tomorrow on your first build.
You should have machines to ship a week today.
Thanks.

 

note that above, 'tomorrow' now means today (tuesday) 

so you now all have exactly the same information that i hold.  we will be shipping all the first build LONDINIUM R next week

if you are considering on of our machines i suggest you take a moment to price it up in your local currency as i think it is about as favourable an exchange rate against the sterling as you will ever see

once again, apologies for the delay as we went through the bill of materials back in november and i understood we had everything in place for a build last week

kind regards

 

reiss.